Second Nord Stream 2 String Filled with Technical Gas
Dec. 29, 2021 | Zug, Switzerland | As of December 29, the gas-in procedure for the second string of the Nord Stream 2 Pipeline has been completed. As planned and in line with the system design requirements, the string is filled with some 177 million m3 of so-called technical gas, reaching a pressure of 103 bar in the pipeline. This pressure is sufficient to start gas transportation in the future.
Nord Stream 2 will inform about further technical steps in due time.